Project Update: Laguna Canyon Channel Replacement Project (March 2023)
Body
Current Project Progress Work Completed to Date As of February, 675 feet of channel replacement has been completed, as well as the drainage structures and the reinforced concrete bridge at Woodland Drive. Other items completed include clearing and grubbing of vegetation, sidewalk, curb and gutter, decorative fencing and fire hydrant...
Construction Alert: Carbon Creek Channel (April 10-28, 2023)
Body
PROJECT SUMMARY OC Public Works will complete temporary repairs to Carbon Creek (B01) Flood Control Channel within unincorporated County right-of-way and adjacent to the City of Anaheim. WHAT Area motorists and other road users may experience delays when traveling through the project area during working hours. Traffic control measures, such...
Construction Alert: Kempton Storm Channel Rehabilitation Project
Body
OC Public Works will complete a rehabilitation project in the unincorporated Orange County area of Rossmoor. Construction begins upstream of the San Gabriel River at the 605 Freeway and continues 1,130-feet downstream of Montecito Road. Work will include repair of concrete cracks and removal and replacement of channel lining.
Maintenance Alert: Talbert Channel Ocean Outlet (Aug.24, 22 - Nov. 23, 22)
Body
WHAT Crews will use large equipment to remove accumulated excess sand from the Talbert Channel outlet in Huntington Beach, as allowed through a regulatory permit. This emergency activity is needed to remove water flow blockage. It is critical flood control maintenance to allow tidal flushing of the marsh to maintain...
Project Update: Laguna Canyon Channel Replacement Project
Body
PROJECT UPDATE JANUARY 2023 LAGUNA CANYON CHANNEL REPLACEMENT PROJECT Woodland Drive to the southern end of Laguna Canyon Frontage Road Current Progress — 43% Complete! Work completed to date includes: • 450 feet of channel replaced! • Drainage structures constructed. • Reinforced concrete bridge (Woodland Dr.). • Vegetation clearing. •...
Project Update: East Garden Grove-Wintersburg Channel
Body
CURRENT STATS Construction is 70% complete with an anticipated completion date of December 2022. 20,000 linear feet of sheet piles installed! That’s 100% complete! 7,000 linear feet improved for seismic resilience! (73% complete.) STEEL SHEET PILE FUN FACT The Steel Sheet Piles installed are a marine grade steel, which is...