FUTURE CHANGE IN INTERSECTION TRAFFIC MANAGEMENT
PROJECT SUMMARY
Existing STOP signs to be replaced with new traffic signal system; Project includes installation of other traffic management equipment.
WHAT
Upcoming activities:
· March 11—15, 2024: Minor utility work
· As early as March 15—early May, 2024: Installation of traffic signal pole foundations, poles, signal lights and associated equipment; Painting of road striping and installation of traffic signs. Traffic signal lights expected to begin operating as early as April 2024
Completed activities:
· Underground utility work and installation of new fiber optic conduit (OC Public Works’ Traffic Management Center remote monitoring system)
· Asphalt/concrete restoration; curb ramp upgrades
Attention: Be prepared for temporary closures!
· Intermittent lane closures to accommodate installation of traffic signal poles, signal lights and equipment
· Temporary sidewalk closures are expected in the project area, yet sidewalks will re-open daily at the conclusion of work. Please use other available sidewalk during closures
· Access will remain open to/from adjacent residential communities
· Please observe all project safety signs and barriers when traveling near project work areas
WHERE
Intersection of Oso Parkway and Coto de Caza Drive/Bend Road.
WHEN
March 11 – May 2024
Monday — Friday, 7 a.m. — 3:30 p.m.
Lane closures will be limited during peak drive times to minimize impacts.
Traffic signal lights expected to begin operating as early as April 2024.
Schedule is tentative and subject to change.
CONTACT INFORMATION
Shannon Widor, (714) 667-9759